Key Milestones Remaining
# Anticipated Completion Date
Description
1 4/3/2020 Received comments from EPA.
2 9/18/2020 Submitted updated LTCP to EPA & IDEM
3 3/17/2021 Received partial approval from EPA.
4 3/1/2035 Full Implemetation of Long-Term Control Plan under Consent Decree
Anticipated # of CSO Discharges Remaining After Implementation
# Outfall Discharges During Typical Year
005 Kennedy North Partial approval received - awaiting final approval of Long Term Control Plan
006 Kennedy Ejector
007 Indianapolis
008 Walnut
009 Tapper
010 Jackson
011 173rd & Forest
012 Hohman /Munster
014 Cal/Munster
022 Columbia CSO Basin 4*
*Remaining discharges will, at a minimum, receive the equivalent of primary treatment and disinfection.