| Key Milestones Remaining |
| # |
Anticipated
Completion Date |
|
| 1 |
04/03/20 |
Received comments from EPA. |
| 2 |
09/18/20 |
Submitted updated LTCP to EPA &
IDEM |
| 3 |
03/17/21 |
Received partial approval from EPA. |
| 4 |
03/01/35 |
Full
Implemetation of Long-Term Control Plan under Consent Decree (not including
additional delay caused by January 2025 Notice of Force Majeure) |
|
|
|
| Anticipated
# of CSO Discharges Remaining After Implementation |
| # |
Outfall |
Discharges During Typical Year |
| 005 |
Kennedy North |
Partial approval received - awaiting final
approval of Long Term Control Plan |
| 006 |
Kennedy Ejector |
| 007 |
Indianapolis |
| 008 |
Walnut |
| 009 |
Tapper |
| 010 |
Jackson |
| 011 |
173rd & Forest |
| 012 |
Hohman /Munster |
| 014 |
Cal/Munster |
| 022 |
Columbia CSO Basin |
4* |
| *Remaining
discharges will, at a minimum, receive the equivalent of primary treatment. |
|
|
|
|
|
|